Flare Gas I&C (PA)

Project Description:       Flare Gas Instrumentation and Electrical

Project Location:            Pennsylvania 

Project Schedule:           August 2015 through July 2016

Role of Riggs Distler:    Our installation comprises installing cable tray on new and existing pipe bridges, tray cables for power, control and instrumentation from the new RIE to the equipment skids, lighting, power distribution, heat tracing, pipe insulation and grounding. We received, calibrated, installed the instrumentation throughout the site. We performed start up and pre-commissioning activities for a fully operation system.