138kV Line Rebuild (IL)

Project Description:      138kV Line Rebuild

Project Location:           Illinois

Project Schedule:          February 2016  through December 2016

Role of Riggs Distler:    Our role as the Contractor included the rebuild of 24 miles of an existing 138kV line within a 110 day outage window.  Riggs Distler crews installed 215 steel monopoles, 31 foundations, and 24 circuit miles of T2 Twist 1133 conductor while removing 202 wooden H-structures and all existing conductor.  Riggs Distler also installed and maintained 24 miles of environmental matting.  This project was completed on schedule and without incident.