138kV Line Rebuild (IL)

Project Description:      138kV Line Rebuild

Project Location:           Illinois

Project Schedule:          September 2015 through December 2015

Role of Riggs Distler:    As the Contractor, our role included the rebuild of 16 miles of an existing 138kV line within a 71 day outage window.  Riggs Distler crews installed 170 steel monopoles, 51 foundations, and 16 circuit miles of T2 Twist 1133 conductor while removing 162 wooden H-structures and all existing conductor.  Riggs Distler also managed 15 miles of environmental matting.  This project was completed on schedule and without incident.