115kV Energized Services (NY)

Project Description:      115kV Line Conductor Clearance & Line Refurbishment Project

Project Location:           New York

Project Schedule:          June 2015 through July 2015

Role of Riggs Distler: Our role as the Contractor included installing intermediate structures, floating dead ends, and replacing existing structures in place while working under energized conditions.  This work was completed using hot-stick and bare hand methods.  This project also included the management of environmental controls in certain wetland areas. This project was completed on schedule and without incident.