69kV Line Rebuild (NJ)

Project Description:     69kV Line Rebuild

Project Location:          New Jersey

Project Schedule:         October 2016 through February 2017

Role of Riggs Distler:  Riggs Distler’s role as the Contractor included the rebuild of 5.4 miles of existing 69kV line within a 120 day outage window.  Riggs Distler crews installed 90 steel monopoles, 13 H4 wooden poles, 51 caissons, and 5.4 circuit miles of #795 ACSR with OPGW while removing 162 wood poles and all existing conductor.  Riggs Distler also managed 4.5 miles of environmental matting thru wetlands. This project was completed on schedule and without incident.