Gas Turbine BOP (NJ)

Project Description:      Gas Turbine Balance of Plant Piping & Equipment Installation

Project Location:           New Jersey

Project Schedule:          July 2014 to October 2017

Role of Riggs Distler:    Riggs Distler role in this project was to install balance of plant piping and equipment setting. Pipe installation consisted of over 35,000 feet of piping ranging from 2” to 72” consisting of critical and non-critical piping systems. The equipment setting scope of work of consisted of over installing 100 pieces of equipment including the steam turbine generator, lube oil building, auxiliary boiler, Diesel generator, stacks, various pumps and motor sets, vessels, drums, and exchangers