Boiler Relocation (NJ & PA)

Project Description:     Boiler Dis-Assemble and Relocation  

Project Location:          New Jersey & Pennsylvania               

Project Schedule:         August 2014 to July 2015

Role of Riggs Distler:  This project required the complete dismantling of Boiler Unit #7 and components located at Eagle Point Refinery NJ and relocation of the4 entire unit at Monroe Energy located in Trainer PA. The Rentech Boiler (480,000 lbs), Economizer (100,000lbs), and all super load duct sections were barged down the Delaware River from Eagle Point NJ to Trainer PA. All other components such as 150’ stack, Pipe Racks and Platforms, Fuel and Chemical Skids, Chemical building, Cooling Tower, Precipitator, Collection Tube assembly’s, Transformer, Roof sections as well as 25 trailer loads of pipe that were trucked over the road to the Monroe site.  Riggs Distler re-assembled the entire Boiler Unit including start up, testing, and commissioning.