13 MW Solar Net Meeter (NJ)

Project Description:      Berry Plastics 13mwdc Solar Facility

Project Location:           New Jersey

Project Schedule:           June 2013 through September 2013

Role of Riggs Distler:    Riggs Distler’s role as the Contractor included a turnkey solution which was completed in 12 weeks.  Riggs Distler’s  work scope included site clearing and demolition, environmental controls, post and racking installation, the installation of 44,000 PV modules, the installation of DC and AC wiring, all civil work, and the installation of the Balance of System.  Riggs Distler’s scope also included a self-performed directional bore of 2,200’ under an existing railroad spur to tie the system directly to the customer’s facility switch making this the largest net metered solar facility in New Jersey.