Project Included

Cable Project—Delaware

October 2019–March 2020

Riggs Distler’s industrial electrical team recently completed extensive electrical installations for a Hydrogen Power Plant at an existing refinery facility in Delaware. Our crews were tasked with providing redundant 15kv power sources to various areas of the refinery and the new plant. Work included:

  • Installing (6) 15kV cables into existing cable trays 
  • Installing (27) 15kV owner provided splices to existing installed cables
  • Installing (18) 15kV owner provided terminations to existing installed cables
  • Furnishing and installing support steel for cable rigging, cable trays, and pulling equipment

 

Challenges Overcome

    The project setting presented a number of challenges. Since the work needed to be completed within an active refinery, at elevated heights, and around an active rail car line servicing the facility, safety and careful scheduling were key concerns. Our Project Managers worked closely with the client and facility staff to schedule Riggs Distler’s electrical work around the frequent work stoppages caused by train activities and plant functions. Our crews took special care to avoid damage to the sensitive electrical cables to be installed in the hectic work environment, and placed an emphasis on efficiency in order to complete the work.

    Results Delivered

    Riggs Distler’s crews performed all of the necessary cable installations to provide redundant power to the new hydrogen plant safely, while avoiding disturbances to the site’s normal operations. Our team delivered the project on schedule and on budget. Given our performance despite the project’s challenges, Riggs Distler was invited to perform additional work for the client. We are proud of our contributions to bringing this important new facility online. 

    Project Included

    Case Studies

    Oil-Water Separator Installation at a Generating Station—Pennsylvania
    May–December 2020
    In the spring of 2020, Riggs Distler was contracted to install a new oil-water separator at  a Generating Station in southeast Pennsylvania....
    CoGen Upgrade Project
    September 2019–November 2020
    Riggs Distler and our joint-venture engineering partner completed upgrades to three gas turbines and a hot water waste generator at an important...
    Cable Project—Delaware
    October 2019–March 2020
    Riggs Distler’s industrial electrical team recently completed extensive electrical installations for a Hydrogen Power Plant at an existing...
    Co-Generation Project — Chester, PA
    2019–2020
    Riggs Distler was hired to install two new co-generation units at an existing paper products facility in southeastern Pennsylvania. The new unit...
    Hydrogen Gas Plant — Delaware
    March 2019-Spring 2020
    Riggs Distler is providing extensive heavy civil, mechanical, and instrumentation services in support of the construction of a hydrogen gas plant in...
    Butane / Propane Transload Facility —New Jersey
    2019 - 2020
    Riggs Distler was subcontracted to perform mechanical services in support of Phase I of this project to expand existing propane and butane caverns...
    Aries Linden Biosolids Gasification Plant — Linden, NJ
    2020-2021
    Riggs Distler provided turnkey heavy civil, mechanical, and electrical services in support of an Aries Clean Energy project to construct a biosolids...
    Air Separation Unit Project — Pennsylvania
    August 2019-June 2020
    Riggs Distler was contracted to provide heavy civil, mechanical piping, and equipment setting services to support the construction of an Air...
    Multi-Service Upgrades to Enhance Refinery-Pennsylvania
    2018
    Riggs Distler combined our Mechanical, Electrical, and Heavy Civil expertise to complete this project to deliver critical upgrades to an oil...
    Substation Installation — Pennsylvania
    2018
    Riggs Distler was awarded this contract to upgrade and stabilize the power supply for a natural gas refinery in Pennsylvania. Our work was part of a...
    Combined Cycle Power Generation Project — New Jersey
    2014–2017
    Riggs Distler was awarded this project to install over 35,000 feet of piping and over 100 pieces of equipment at a power plant in southern New....