Project Included

Great Egg Harbor Crossing Rebuild Project—New Jersey

September–December 2020

Riggs Distler was contracted to assemble and install eight electric transmission towers to provide improved electrical service to customers in Atlantic and Cape May counties. The existing lattice structures were originally installed in the 1960s; these upgrades modernize and greatly improve the system’s performance.

The towers and equipment were loaded onto barges in sections and hauled to the foundations in the bay, where Riggs Distler’s crews used two 40-ton cranes with man baskets mounted on separate barges to assemble the towers and install components.

Our work included:

  • Assembling and installing 8 transmission towers on new foundations (5 on water and 3 on land)
  • Installing six 1590 ACSR Conductors and two OPGW (Fiber Optics)
  • Installing new transmission conductor and tie-ins.
  • Removing existing conductor, lattice structures, and foundations (on land).
  • Install 2,300 environmental mats for the installation of two transmission towers.

Challenges Overcome

In order to perform the water-based work, Riggs Distler’s team had to contend with daily tidal cycles, which required extensive and continuous planning. Every day, our work had to be carefully scheduled in order to ensure tides allowed the proper draft for boats and barges to access the work site and return home at the end of the day. Any missed opportunity or lapse in scheduling could have caused a 24-hour delay. Since environmental laws required all water-based work to be performed between September and December, maintaining our schedule was crucial to successful project completion.

The land-based tower sites were located in environmentally protected areas, as well as being in a tidal water area. With that, extensive action was taken at each location to ensure the locations remained undisturbed. Our environmental matting team made sure that the area was carefully protected using mats, silt socks, and silt fencing, and we performed daily inspections to ensure the integrity of the surrounding environment.

Results Delivered

Despite the challenges of performing highly technical work on the open water, Riggs Distler again proved that there is no challenge our professionals cannot handle. We provided all necessary work for the project in-house, and our crews kept a primary focus on safety at all project stages. The new towers and equipment upgraded the capacity of the transmission line from 138kV to 230kV, providing increased reliability and improved electrical service for citizens and businesses throughout coastal southern New Jersey. The modern monopole towers also improved the aesthetics and visual impact of the transmission system for nearby residents and beachgoers.

For an in-depth look at Riggs Distler’s approach to completing this challenging and important project, be sure to watch this video overview: https://riggsdistler.com/great-egg-harbor-crossing-rebuild-project/

Project Included

Case Studies

15-Mile 69kV Transmission Line Rebuild—Southern New Jersey
2021
Riggs Distler was contracted to modernize and upgrade the performance of a major electric transmission line connecting two substations in southern...
COC for Overhead Transmission Projects—DE, PA, NJ, MD, IL
January 2021–December 2025
Riggs Distler is the Contractor of Choice for all installation, maintenance, and repair work performed on our client’s electrical transmission...
115kV Transmission Line Rebuild—New Hampshire
May–June 2020
Riggs Distler was contracted to upgrade aging tower infrastructure along an important 115kV electrical transmission line in New Hampshire. In order...
Great Egg Harbor Crossing Rebuild Project—New Jersey
September–December 2020
Riggs Distler was contracted to assemble and install eight electric transmission towers to provide improved electrical service to customers in...
Y138 Line Structure Replacements—New Hampshire
April–July 2020
Riggs Distler performed environmental matting and civil services in support of a project to upgrade aging and damaged support structures along...
Transmission Line Refurbishment Project Phase I — Massachusetts
Sept 2019–June 2020
Riggs Distler was contracted by a major power provider to provide environmental matting services in support of a 315 & 303/327/3520kV...
Access Matting for Structure Replacement – New Hampshire
April–June 2020
Riggs Distler’s environmental construction and matting teams provided civil services to improve access to an aging 115kV transmission line in New...
Environmental Services for Structure Replacement — New Hampshire
January–June 2020
Riggs Distler’s environmental matting team was contracted to build roads and provide extensive matting in support of a project to upgrade an aging...
Aquidneck Island Reliability Project — Rhode Island
April 2018–April 2019
Riggs Distler was contracted to provide Environmental Matting and Environmental Controls for the 61/62 Aquidneck Island Reliability Project, which...
J10 Soil Boring Access Project — Western Massachusetts
April–June 2018
Riggs Distler’s Environmental Matting Division was contracted to develop an access road across a difficult and inundated landscape to allow a test...