Project Included

Fractionator Balance of Plant Piping and Equipment Installation—Pennsylvania

2016–2017

Riggs Distler was contracted to mobilize a fractionator unit on behalf of a natural gas client in Pennsylvania. A critical step in the refinery process, fractional distillation is useful for separating a mixture of substances with narrow differences in boiling points, allowing for the retrieval of residual substances and their storage for later re-use. Our work involved:

  • Installation of approximately 1,328 feet of pipe rack
  • Installation of 17,000 feet of large and small bore piping
  • Final tie-ins to existing spheres
  • Installation of 3 metering skids and 6 vertical pumps
  • Analyzer and PDC building installations
  • Transformer installations

Challenges Overcome

Due to its large size, the metering skid was provided in three separate pieces, but when assembled, these pieces were misaligned from a third party fabricator. Riggs Distler’s team cut, welded, and shimmed the metering skid components to fit until it was functional, saving valuable time.

The project’s major technical challenge was coming up with a plan to install piping around the fractionator spheres. This work required maximum coordination between our structural steel subcontractors and our pipefitters. Ultimately, our team built a scaffold from the top of each sphere down its side to field-fit the pipe in position. As each of the four to five levels of steel in the pipe rack was installed, pipe was laid in the rack prior to the next level of steel installation. This work required up to 62 pipefitters on-site every day at the project’s peak.

Due to a high volume of construction in the region, Riggs Distler also contended with a lack of local available employees. As a result, we shipped in workers from all over the country to assist us, spending extra time on training to get crews up to speed on our high standards of safety and efficiency.

Results Delivered

Despite the labor shortage and technical challenges, Riggs Distler completed the project on time and on budget. Our work greatly improved the function of the client’s plant and delivered expanded gas services to Pennsylvania citizens.

Project Included

Case Studies

New Process Line Construction — New Jersey
2021
Riggs Distler was contracted to construct new process lines from a major oil refinery in southern New Jersey that will feed a large-scale...
Oil-Water Separator Installation at a Generating Station—Pennsylvania
May–December 2020
In the spring of 2020, Riggs Distler was contracted to install a new oil-water separator at  a Generating Station in southeast Pennsylvania....
CoGen Upgrade Project
September 2019–November 2020
Riggs Distler and our joint-venture engineering partner completed upgrades to three gas turbines and a hot water waste generator at an important...
Hydrogen Gas Plant — Delaware
March 2019-Spring 2020
Riggs Distler is providing extensive heavy civil, mechanical, and instrumentation services in support of the construction of a hydrogen gas plant in...
Butane / Propane Transload Facility —New Jersey
2019 - 2020
Riggs Distler was subcontracted to perform mechanical services in support of Phase I of this project to expand existing propane and butane caverns...
Aries Linden Biosolids Gasification Plant — Linden, NJ
2020-2021
Riggs Distler provided turnkey heavy civil, mechanical, and electrical services in support of an Aries Clean Energy project to construct a biosolids...
Air Separation Unit Project — Pennsylvania
August 2019-June 2020
Riggs Distler was contracted to provide heavy civil, mechanical piping, and equipment setting services to support the construction of an Air...
Multi-Service Upgrades to Enhance Refinery-Pennsylvania
2018
Riggs Distler combined our Mechanical, Electrical, and Heavy Civil expertise to complete this project to deliver critical upgrades to an oil...
590 MW HRSG Installation — New Jersey
2018
Riggs Distler was awarded the contract for the Combined Cycle Build as a full construction-takeover project when the previous contractor could not...
Boiler Relocation — New Jersey and Pennsylvania
2014–2015
Riggs Distler was awarded this project to dismantle a boiler unit and its components, located  in southern New Jersey, and relocate the entire unit...
Fractionator Balance of Plant Piping and Equipment Installation — Pennsylvania
2016–2017
Riggs Distler was contracted to mobilize a fractionator unit on behalf of a natural gas client in Pennsylvania. A critical step in the refinery...
Flare Gas Recovery Project — Pennsylvania
2015
Riggs Distler was awarded this project to help our client meet Environmental Protection Agency (EPA) emissions requirements at a refinery in...
Combined Cycle Power Generation Project — New Jersey
2014–2017
Riggs Distler was awarded this project to install over 35,000 feet of piping and over 100 pieces of equipment at a power plant in southern New....