Project Included

New Process Line Construction— New Jersey

2021

Riggs Distler was contracted to construct new process lines from a major oil refinery in southern New Jersey that will feed a large-scale distribution system. The refineries work in combination to process a wide variety of crude oils. The two plants produce a variety of products, including gasoline, heating oil, and aviation jet fuel. One specializes in manufacturing Group I lubricant-base oils and is the largest producer of asphalt on the East Coast. The new product lines will improve the supply process to the facility and overall efficiency of the refinery’s operations.

Riggs Distler’s Heavy Civil group installed a dewatering well system, excavated and installed the entire shoring system on both the refinery and distribution side, uncovering all the previously operational underground lines. The Mechanical group fabricated and installed all of the pipe supports and new piping. Additionally the Overhead Transmission group assisted to relocate an existing pole and power lines.

Work also involves:

  • Installation of all pipe support foundations, light pole foundations and pit floors.
  • Removal of over 1,000 feet of underground existing piping from existing casings.
  • Install new, 6-inch and 8-inch piping within 10-inch casings.
  • Hydrostatic testing each of the newly installed pipe lines
  • Pigging each of the newly installed pipe lines for debris and dryness.
  • Isolation of steam line.
  • Install new tie-in fabrications
  • Filling the abandoned portion of underground piping with Bentonite Clay
  • Performing a Nitrogen purge and fill on 2 of the newly installed underground lines.
  • Filling the newly installed underground casings with a protective wax
  • Form and pour a concrete pit to encase the piping underground.
  • Removal of all dewatering and shoring systems.
  • Construct a new site security fence and access road

                                        Challenges Overcome

                                        Riggs Distler’s main concern on this project was working within tight outage schedules in order to avoid costly interruptions for the client. By focusing on communication with the client and careful planning, all work was completed safely and on schedule.

                                        Performing major construction work between a busy refining facility and distribution center can present significant logistical challenges. In this case, a working Conrail railroad line that runs directly through the site required special attention. Riggs Distler’s team carefully removed eight process lines running underneath the existing railroad tracks and replaced them with a new, double-wall piping system. Our team was also able to install all of the process lines with more than 100 welds at 100% x-ray with no rejections.

                                        Results Delivered

                                        Riggs Distler completed this complex, large-scale project on schedule and on budget,  delivering increased efficiency for the refinery system and operations. Riggs Distler’s multi-disciplined approach allowed us to complete all necessary Heavy Civil and Mechanical work on both the receiving and distribution sides of the process lines.

                                         

                                         

                                        Project Included

                                        Case Studies

                                        New Process Line Construction — New Jersey
                                        2021
                                        Riggs Distler was contracted to construct new process lines from a major oil refinery in southern New Jersey that will feed a large-scale...
                                        Oil-Water Separator Installation at a Generating Station—Pennsylvania
                                        May–December 2020
                                        In the spring of 2020, Riggs Distler was contracted to install a new oil-water separator at  a Generating Station in southeast Pennsylvania....
                                        CoGen Upgrade Project
                                        September 2019–November 2020
                                        Riggs Distler and our joint-venture engineering partner completed upgrades to three gas turbines and a hot water waste generator at an important...
                                        Hydrogen Gas Plant — Delaware
                                        March 2019-Spring 2020
                                        Riggs Distler is providing extensive heavy civil, mechanical, and instrumentation services in support of the construction of a hydrogen gas plant in...
                                        Butane / Propane Transload Facility —New Jersey
                                        2019 - 2020
                                        Riggs Distler was subcontracted to perform mechanical services in support of Phase I of this project to expand existing propane and butane caverns...
                                        Aries Linden Biosolids Gasification Plant — Linden, NJ
                                        2020-2021
                                        Riggs Distler provided turnkey heavy civil, mechanical, and electrical services in support of an Aries Clean Energy project to construct a biosolids...
                                        Air Separation Unit Project — Pennsylvania
                                        August 2019-June 2020
                                        Riggs Distler was contracted to provide heavy civil, mechanical piping, and equipment setting services to support the construction of an Air...
                                        Multi-Service Upgrades to Enhance Refinery-Pennsylvania
                                        2018
                                        Riggs Distler combined our Mechanical, Electrical, and Heavy Civil expertise to complete this project to deliver critical upgrades to an oil...
                                        590 MW HRSG Installation — New Jersey
                                        2018
                                        Riggs Distler was awarded the contract for the Combined Cycle Build as a full construction-takeover project when the previous contractor could not...
                                        Boiler Relocation — New Jersey and Pennsylvania
                                        2014–2015
                                        Riggs Distler was awarded this project to dismantle a boiler unit and its components, located  in southern New Jersey, and relocate the entire unit...
                                        Fractionator Balance of Plant Piping and Equipment Installation — Pennsylvania
                                        2016–2017
                                        Riggs Distler was contracted to mobilize a fractionator unit on behalf of a natural gas client in Pennsylvania. A critical step in the refinery...
                                        Flare Gas Recovery Project — Pennsylvania
                                        2015
                                        Riggs Distler was awarded this project to help our client meet Environmental Protection Agency (EPA) emissions requirements at a refinery in...
                                        Combined Cycle Power Generation Project — New Jersey
                                        2014–2017
                                        Riggs Distler was awarded this project to install over 35,000 feet of piping and over 100 pieces of equipment at a power plant in southern New....