Project Included

41-Mile 230kV/138kV Transmission Line Rebuild — New Jersey

November 2017–May 2019

Riggs Distler was selected as the general contractor on this important transmission line rebuild. Project will deliver a more capable and reliable electric grid for the citizens of southern New Jersey. Our work on this project involves:

  • Reinforcing 41 miles of 230kv/138kv electrical transmission lines
  • Replacing 243 lattice towers with steel monopoles installed on foundations or vibratory caissons
  • Installing six new 1590 ACSR conductors and two new OPGW lines
  • Managing environmental and archaeological compliance
  • Installing, maintaining and removing erosion and sediment controls
  • Managing civil contractors installing 243 foundations
  • 70–90 workers on-site every day

Challenges Overcome

The project presented a number of unique challenges, including an accelerated project schedule, tight outage windows for construction, and complex environmental concerns. The project area spans the marshes and bogs of the New Jersey pinelands, and Riggs Distler’s environmental matting team is heavily involved, installing extensive matting to create safe conditions for construction and protect the local environment and handling E&S. In areas where matting is not possible, Riggs Distler has contracted with an aviation consultant to help set poles and equipment using helicopters.

Coordination with multiple environmental and archaeological regulatory agencies is also required due to the presence of protected species and undisclosed archaeological sites. Our team is working with monitors from the New Jersey Division of Fish and Wildlife, who are on-site daily, to preserve the integrity of local habitats and avoid construction during the mating seasons of sensitive species. Careful scheduling and execution is also a top priority for our Project Managers, as all project phases must be completed within eight specific outage windows to ensure uninterrupted service to end users.

Results Delivered

Despite the tough terrain and complicated schedule requirements, Riggs Distler has successfully completed all phases of the project while managing compliance issues and ensuring the safety and efficiency of our staff in the field. Our team loves a good challenge, and this project was an excellent demonstration of Riggs Distler’s expertise handling large projects with multiple components. The new equipment will better sustain weather damage and last over a half-century, and the upgraded line will deliver increased power to residents and businesses throughout southern New Jersey.

 

Riggs Distler received the New Jersey Alliance for Action Essential Infrastructure Award and the National NECA Excellence Award for this project.

 

Project Included

Case Studies

15-Mile 69kV Transmission Line Rebuild—Southern New Jersey
2021
Riggs Distler was contracted to modernize and upgrade the performance of a major electric transmission line connecting two substations in southern...
COC for Overhead Transmission Projects—DE, PA, NJ, MD, IL
January 2021–December 2025
Riggs Distler is the Contractor of Choice for all installation, maintenance, and repair work performed on our client’s electrical transmission...
115kV Transmission Line Rebuild—New Hampshire
May–June 2020
Riggs Distler was contracted to upgrade aging tower infrastructure along an important 115kV electrical transmission line in New Hampshire. In order...
Great Egg Harbor Crossing Rebuild Project—New Jersey
September–December 2020
Riggs Distler was contracted to assemble and install eight electric transmission towers to provide improved electrical service to customers in...
K43 Fiber Project - Vermont
January-June 2020
Riggs Distler was contracted to install 21 miles of new ADDS fiber-optic cable and support braces on a 115kV transmission line stretching from...
Switching Station Spare Transformer — New Jersey
February–May, 2020
February–May...
24-Mile 138kV Transmission Line Rebuild — Monee, Illinois
January 2016-January 2017
Our host utility needed to replace an aging 138kv transmission line stretching 24 miles across northeastern Illinois. Working under a tight, ...
Hurricanes Katrina, Rita and Wilma Emergency Power Restoration — Louisiana, Alabama, Florida, Mississippi
August-December 2005
In 2005, Riggs Distler was hired to help restore power to areas affected by the devastating Hurricanes Katrina, Rita, and Wilma. It’s estimated...
Hurricane Sandy Emergency Power Restoration — New Jersey
November 2012
As Hurricane Sandy’s landfall along the mid-Atlantic coast became imminent, Riggs Distler immediately set to work preparing vehicles, equipment,...
Post-Hurricane Power Restoration — Puerto Rico
2017–2018
After multiple Category 3+ hurricanes decimated the Puerto Rico Electric Power Authority grid in 2017, Riggs Distler quickly mobilized to help...
13kV & 23kV Circuit Refurbishment — Massachusetts
2015–2018
Riggs Distler was contracted to reconductor approximately 20 miles of 13kV and 23kV circuits and replace over 500 wooden utility poles for an...
Susquehanna River Transmission Line Crossing — Pennsylvania
2017
Riggs Distler completed this difficult reconductoring project for a transmission line spanning the Susquehanna River. The 1.1-mile river crossing is...
30-Mile 138kv New Build/69kV Transmission Line Rebuild — Virginia & Maryland
2017–2018
Riggs Distler rebuilt 30.9 miles of 138/69kV transmission line over five different outage windows in 2017–18 to deliver improved electric...
41-Mile 230kV/138kV Transmission Line Rebuild — New Jersey
November 2017–May 2019
Riggs Distler was selected as the general contractor on this important transmission line rebuild. Project will deliver a more capable and reliable...