Project Included

Aquidneck Island Reliability Project — Rhode Island

April 2018–April 2019

Riggs Distler was contracted to provide Environmental Matting and Environmental Controls for the 61/62 Aquidneck Island Reliability Project, which will upgrade and improve power distribution for residents and businesses in the Portsmouth and Middletown areas of Rhode Island. Our work includes:

  • Building over 40 work pads and pull pads for the drilling and line crews
  • Environmental controls
  • Construction of multiple timber bridges across streams
  • Replacing multiple culverts
  • Improving right-of-way access roads
  • Bank stabilization with structured retaining walls

The road improvements involved laying hundreds of cubic yards of stone and gravel to provide a stable surface. Riggs Distler’s team also installed thousands of feet of compost filter sock along access roads and streams to prevent silt runoff from seeping into surrounding wetlands.

Challenges Overcome

Our team faced significant challenges while planning and building the road, including difficult terrain, steep embankments, a ledge, snow cover in the winter, and meltwater in the spring. Every inch of the access road was built in a wetland or over extremely muddy uplands.
In addition to the tough conditions, the client needed the road completed as soon as possible in order to perform structural assessments in advance of planned refurbishment in the coming months. The project area was also home to several rare and protected species, requiring environmental and construction controls, and portions of the road crossed lands managed by the Massachusetts DCR, requiring careful public agency coordination.

Results Delivered

Clients count on Riggs Distler’s road building and environmental matting expertise to support the reliability of their power networks. The Aquidneck Island project is an excellent example of our team’s ability to mobilize quickly to stabilize and protect work sites so that important projects can proceed as scheduled.

Project Included

Case Studies

15-Mile 69kV Transmission Line Rebuild—Southern New Jersey
2021
Riggs Distler was contracted to modernize and upgrade the performance of a major electric transmission line connecting two substations in southern...
COC for Overhead Transmission Projects—DE, PA, NJ, MD, IL
January 2021–December 2025
Riggs Distler is the Contractor of Choice for all installation, maintenance, and repair work performed on our client’s electrical transmission...
115kV Transmission Line Rebuild—New Hampshire
May–June 2020
Riggs Distler was contracted to upgrade aging tower infrastructure along an important 115kV electrical transmission line in New Hampshire. In order...
Great Egg Harbor Crossing Rebuild Project—New Jersey
September–December 2020
Riggs Distler was contracted to assemble and install eight electric transmission towers to provide improved electrical service to customers in...
K43 Fiber Project - Vermont
January-June 2020
Riggs Distler was contracted to install 21 miles of new ADDS fiber-optic cable and support braces on a 115kV transmission line stretching from...
Switching Station Spare Transformer — New Jersey
February–May, 2020
February–May...
24-Mile 138kV Transmission Line Rebuild — Monee, Illinois
January 2016-January 2017
Our host utility needed to replace an aging 138kv transmission line stretching 24 miles across northeastern Illinois. Working under a tight, ...
Hurricanes Katrina, Rita and Wilma Emergency Power Restoration — Louisiana, Alabama, Florida, Mississippi
August-December 2005
In 2005, Riggs Distler was hired to help restore power to areas affected by the devastating Hurricanes Katrina, Rita, and Wilma. It’s estimated...
Hurricane Sandy Emergency Power Restoration — New Jersey
November 2012
As Hurricane Sandy’s landfall along the mid-Atlantic coast became imminent, Riggs Distler immediately set to work preparing vehicles, equipment,...
Post-Hurricane Power Restoration — Puerto Rico
2017–2018
After multiple Category 3+ hurricanes decimated the Puerto Rico Electric Power Authority grid in 2017, Riggs Distler quickly mobilized to help...
13kV & 23kV Circuit Refurbishment — Massachusetts
2015–2018
Riggs Distler was contracted to reconductor approximately 20 miles of 13kV and 23kV circuits and replace over 500 wooden utility poles for an...
Susquehanna River Transmission Line Crossing — Pennsylvania
2017
Riggs Distler completed this difficult reconductoring project for a transmission line spanning the Susquehanna River. The 1.1-mile river crossing is...
30-Mile 138kv New Build/69kV Transmission Line Rebuild — Virginia & Maryland
2017–2018
Riggs Distler rebuilt 30.9 miles of 138/69kV transmission line over five different outage windows in 2017–18 to deliver improved electric...
41-Mile 230kV/138kV Transmission Line Rebuild — New Jersey
November 2017–May 2019
Riggs Distler was selected as the general contractor on this important transmission line rebuild. Project will deliver a more capable and reliable...