skip to main content

Cogen Upgrade Project

Located in New Jersey

  • Capability
    • Distributed Power, Renewable & Industrial
  • Completion 2019–2020

Project Overview

In New Jersey, the team worked alongside our joint-venture engineering partner to complete upgrades to three gas turbines and a hot water waste generator at an electrical generation site. Installing the upgraded units lowered the owner’s maintenance costs associated with the unreliability of older units and planned shutdowns, lessened the facility’s impact on the environment, and allowed the plant to perform more efficiently. The new units each produced 5.7 MW of electricity. The successful project completion was due to the efforts of our Heavy Industrial and Electrical Generation teams.

Explore Project Details

Project Scope of Work Included:

  • Demolition and Replacement of Combustion Generator Foundation Slab & Auxiliary Housekeeping Pads
  • Removal & Replacement of Steel Support Structures for Filter Houses Below and Above the Roof Line, Replacement of Lubricant Oil Cooler Structures
  • Extensive Roofing Work to Allow for New Piping, Steel, & Electrical Work to be Completed
  • Removal and Replacement of Ducting, Bypass Stacks, High-Temperature Hot Water Code Piping, High/Low-Pressure Gas Piping, Generator Lube Oil Piping, & Miscellaneous Piping Systems for Air, CO2, Non-Potable Water, and Fuel oil
  • Demolition & Replacement of (3) 4.7-MW Turbines Generators with New 5.7-MW Turbine Generators and New Hot Water Heat Recovery Generators Controls
  • Installation of New Variable Speed Drive for Motor within the New Turbine Generators
  • Demolition of Existing Balance of Plant Control & Installation of new, Balance of Plant Control, Instrumentation, and Communications Systems
  • Demolition & Replacement of (3) Control Centers with New Control System Capabilities
  • Installation of (3) Continuous Emission Monitoring Systems like Mechanical Installations of New Sample Tubing From Each Stack
  • Demolition & Replacement of Uninterrupted Power Supply Systems (UPS)
  • Over 50,000 Feet of Control Cabling & 20,000 Feet of Power Cabling Installations with Associated Conduit

Challenges and Results

This project came with significant challenges, such as installing several pieces of large equipment over 55,000 lbs. The key to the project’s success included careful planning and logistics, a gantry system used for safe removal, and close communication between plant staff to ensure efficiency. Executed during the COVID-19 pandemic, challenges included tight working spaces, special PPE, and social distancing.

Previous
Rutgers5
Rutgers3
Rutgers2
Rutgers1
Rutgers
Next
Previous Rutgers5 Rutgers3 Rutgers2 Rutgers1 Rutgers Next
Previous 0 1 2 3 4 Next

Project Overview

In New Jersey, the team worked alongside our joint-venture engineering partner to complete upgrades to three gas turbines and a hot water waste generator at an electrical generation site. Installing the upgraded units lowered the owner’s maintenance costs associated with the unreliability of older units and planned shutdowns, lessened the facility’s impact on the environment, and allowed the plant to perform more efficiently. The new units each produced 5.7 MW of electricity. The successful project completion was due to the efforts of our Heavy Industrial and Electrical Generation teams.

Explore Project Details

Project Scope of Work Included:

  • Demolition and Replacement of Combustion Generator Foundation Slab & Auxiliary Housekeeping Pads
  • Removal & Replacement of Steel Support Structures for Filter Houses Below and Above the Roof Line, Replacement of Lubricant Oil Cooler Structures
  • Extensive Roofing Work to Allow for New Piping, Steel, & Electrical Work to be Completed
  • Removal and Replacement of Ducting, Bypass Stacks, High-Temperature Hot Water Code Piping, High/Low-Pressure Gas Piping, Generator Lube Oil Piping, & Miscellaneous Piping Systems for Air, CO2, Non-Potable Water, and Fuel oil
  • Demolition & Replacement of (3) 4.7-MW Turbines Generators with New 5.7-MW Turbine Generators and New Hot Water Heat Recovery Generators Controls
  • Installation of New Variable Speed Drive for Motor within the New Turbine Generators
  • Demolition of Existing Balance of Plant Control & Installation of new, Balance of Plant Control, Instrumentation, and Communications Systems
  • Demolition & Replacement of (3) Control Centers with New Control System Capabilities
  • Installation of (3) Continuous Emission Monitoring Systems like Mechanical Installations of New Sample Tubing From Each Stack
  • Demolition & Replacement of Uninterrupted Power Supply Systems (UPS)
  • Over 50,000 Feet of Control Cabling & 20,000 Feet of Power Cabling Installations with Associated Conduit

Challenges and Results

This project came with significant challenges, such as installing several pieces of large equipment over 55,000 lbs. The key to the project’s success included careful planning and logistics, a gantry system used for safe removal, and close communication between plant staff to ensure efficiency. Executed during the COVID-19 pandemic, challenges included tight working spaces, special PPE, and social distancing.

Previous
Rutgers5
Rutgers3
Rutgers2
Rutgers1
Rutgers
Next
Previous Rutgers5 Rutgers3 Rutgers2 Rutgers1 Rutgers Next
Previous 0 1 2 3 4 Next