skip to main content
Substation closeup

69 kV Greenfield Substation

2016 in Camden, NJ Riggs Distler
Substation closeup

Results Delivered

Riggs Distler completed the substation build in 4 months using 30 direct craft workers and roughly 25,000 man-hours. By handling all of the necessary substation and heavy civil work in-house, we were able to realize cost savings for our client that other companies could not provide. Our team ultimately delivered the project under budget, and the substation was energized according to schedule, providing improved electrical service to businesses and residents throughout the client’s service territory, all without a single recordable injury.