Substation Contractor of Choice—New Jersey
Ongoing
Riggs Distler is the contractor of choice for all electrical substation work on behalf of a major regional utility operating throughout New Jersey....
Substation Contractor of Choice—Southern New Jersey
January 2021–December 2025
Riggs Distler serves as the Contractor of Choice for substation-related civil and electrical work on behalf of a major East Coast power provider....
Substation Contractor of Choice—Philadelphia Region
January 2021–December 2025
Riggs Distler serves as the Contractor of Choice for substation work on behalf of a major East Coast energy provider. Our work supports system...
Substation Project — New Jersey
October 2019-May 2020
Riggs Distler was contracted by a host utility to demolish an existing 69/12kV electrical substation and perform all civil and electrical work for...
Switching Station Spare Transformer — New Jersey
February–May, 2020
February–May...
AMI Meter Installation — Pennsylvania
2016–2020
Riggs Distler was contracted to replace over 220,000 electric meters with new smart meters and perform associated equipment repairs. Our work has...
69 kV Greenfield Substation — Camden, NJ
2016
Riggs Distler built this 69kV substation from the ground up, performing all related civil work and all aspects of electrical installation. Our work...
Substation Upgrades — Pennsylvania
2018
Riggs Distler was awarded this project to perform substation upgrades to stabilize the host utility’s power grid for reliability and efficiency....